Preparation of the concrete foundation of the 5 silos foundation, construction of the foundation of the storage building and preparation of the foundation of the pre-heating tower for the new center of Port-Daniel in Gaspésie.

The plasma fractionation facility will be built to produce daily batches of 4,000 L of plasma per day for a total of approximately 1,000,000 liters per year, for the production of Albumin and Intravenous Immunoglobulin (IVIG-SM). The plant shall be completed, validated and in trial production for the first quarter of 2017.